Parallel Execution

Dependency scheduling, isolated worktrees, approval gates, integration, and recovery.

On this page

Cadre executes an approved plan as a dependency DAG. Parallel is the default mode, but parallelism is used only when it provides safe, bounded benefit.

Execution Modes

ModeBehavior
parallelCreate workers only when at least two safe nodes are ready; otherwise execute the node in main.
sequentialExecute one ready node at a time in main unless the workflow needs an integration boundary.

The execution journal records requested mode, effective mode, maximum workers, approval mode, plan revision, plan commit, graph digest, base commit, and every node. Changing either mode mid-execution requires a clean safe boundary and approval.

Approval Modes

ModeHuman approval boundary
governedEvery regular task diff and material mutation, plus all manual-verification barriers.
phaseDefault. One approval at each phase's final User Manual Verification task; other in-scope work is autonomous.
autonomousOnly Track-level User Manual Verification; phase-level barriers are verified and recorded autonomously.

Approval modes never authorize scope expansion, waived required checks, destructive or remote actions, or guessing through a material ambiguity. Those conditions stop as blockers or clarification requests rather than routine approval prompts. Legacy execution journals without approvalMode retain the conservative governed behavior.

Worker Capacity

The generated workflow uses 3 as a conservative default, not an architectural limit. The execution runtime accepts maxWorkers values from 1 through 32. At each scheduling checkpoint, the effective delegated concurrency is:

min(safe ready nodes, execution maxWorkers, available host worker slots)

A phase worker consumes one slot, and every active task worker consumes one slot. A phase worker whose lease has been released does not consume scheduler capacity. A task worker waiting for approval remains an active assignment until its checkpoint is committed and completed. Worktrees by themselves do not consume worker slots.

Main is the coordinator and is not counted as a delegated worker in maxWorkers, although the host may reserve one of its total agent slots for main. Consequently, a host exposing four total agent slots commonly leaves three child-worker slots. Raising maxWorkers above host capacity or the number of ready nodes has no effect.

Increase the approved project worker bound only when the plan exposes enough independent work and the repository can tolerate the additional CPU, memory, test, port, approval, and merge pressure. Use the sizing and rollout procedure in Choose The Worker Bound.

Scheduler Ownership

The main agent is the only scheduler and Cadre-state owner. It:

  • derives ready nodes from MCP execution status;
  • creates all worktrees and workers;
  • supplies exact context, allowed paths, dependencies, and verification;
  • reviews every worker diff and evidence, presenting it at the boundary selected by the persisted approval mode;
  • directs task commits after human approval or approval-mode authorization;
  • integrates task branches into phase parents and phase branches into main;
  • resolves and re-verifies conflicts;
  • records learning, manual verification, state, and provenance;
  • cleans worktrees only after integration is proven.

Workers never spawn workers, edit .cadre/**, merge branches, resolve integration conflicts, remove worktrees, or record human approval.

Hierarchical Scheduling

Cadre treats a track as two connected dependency graphs:

  • phase dependencies determine which phases may run;
  • task dependencies determine which work is ready inside every running phase.

Main combines ready tasks from all running phases into one global queue and allocates the execution's bounded worker slots. Independent phases can therefore run concurrently while each phase also moves through sequential and parallel task waves.

Phase Execution Modes

Every non-trivial active phase has a main-owned integration worktree. Within that phase, main selects one mutating mode at a time:

ModeUse
Direct mainOne ready task where delegation provides no benefit.
Sequential phase workerA tightly coupled task chain where retaining worker context is useful.
Task-worker fan-outTwo or more independent ready tasks that can safely execute from one phase snapshot.

Different phases may use different modes concurrently. One phase may also change modes, but only at a clean, journaled checkpoint. A phase worker finishes and records its current task, reports a clean phase HEAD, releases its temporary execution lease, and remains inactive before task workers start. A new phase worker may be assigned only after active task workers have completed and their integration and cleanup are recorded.

Task workers in one dependency wave all branch from the same clean phase HEAD. Main merges their approved branches into the phase worktree one at a time, then derives the next wave from the updated phase HEAD. Workers never spawn workers.

After phase verification, main integrates and records the phase, keeps its execution node integrated through safe worktree cleanup, and only then marks it completed and starts dependent phases. Cleanup also accepts an already completed node as interruption recovery without reopening terminal state.

See the Complex Parallel Execution Walkthrough for a complete mixed sequential/parallel example.

Worktree Layout

Git worktrees cannot be safely nested, so Cadre uses sibling paths:

.cadre/.worktrees/<track-id>/<execution-id>/
├── phases/P1
└── tasks/P1--T1.1

Branches and paths are derived from the track, execution, and node identity. Creation is digest-gated against an exact base commit.

Task Checkpoint

For each regular worker task:

  1. The worker reads the assigned context and product files.
  2. It edits only product files in its worktree.
  3. It runs focused verification.
  4. It stops with changes uncommitted and returns the diff, checks, risks, learning candidates, and proposed commit message.
  5. Main records awaiting_approval and presents the evidence.
  6. After approval, the worker commits only that task.
  7. Main verifies the clean worktree and records the commit SHA.
  8. Main previews and applies integration when a branch boundary exists.

Every regular task receives a distinct Conventional Commit and recorded SHA, including tasks handled sequentially by one phase worker.

Integration And Cleanup

Task branches merge without squashing into their derived parent. Delegated work in a multi-task or phase-verified delivery phase uses a phase integration worktree; direct canonical integration is reserved for an explicitly direct single-task phase. Phase branches merge without squashing into the canonical branch. Before integration the MCP verifies clean source/target worktrees, protected Cadre paths, branch tips, and changed files.

If a merge conflicts:

  • task conflicts are resolved in the owning phase worktree;
  • phase conflicts are resolved in the canonical worktree;
  • all conflicted files and both sides are read;
  • combined verification is rerun;
  • the resolution is presented before its merge commit is recorded.

Cleanup refuses dirty, conflicted, or unintegrated workers. It removes only a worktree whose branch ancestry proves that its work exists in the parent.

Manual Verification

Each delivery phase ends with a derived User Manual Verification barrier over all sibling tasks. Technical evidence is prepared in the phase context, but the main agent presents and records the human decision.

The final track-level manual verification depends on every delivery phase and runs only in the main agent against the fully integrated canonical worktree. Manual-verification nodes can record current commit/merge evidence instead of creating empty commits.

Host Permission Preflight

Before spawning workers, main inspects scripts, lockfiles, likely checks, and required external operations. Shared dependency installs, registry access, image pulls, and code generation are centralized before workers start.

Host permission authorizes only the operation requested. It does not approve a Cadre artifact, task commit, integration, verification result, or lifecycle transition. A worker that encounters an unexpected permission prompt stops and reports the exact command to main.

Resume And Failure

Cadre reconciles journal nodes with worker IDs, Git worktree registrations, branch tips, dirty files, commits, and merges before scheduling:

  • committed or integrated nodes are not repeated;
  • newly ready nodes run after durable transitions;
  • a clean branch containing the expected commit advances bookkeeping;
  • a conflict remains explicit until resolved and approved;
  • an unknown or contradictory state stops rather than being guessed away.

A revision or refresh that changes execution-governing context first quiesces and reconciles active workers. A changed graph starts a new execution identity; the prior journal remains historical.